November 22, 2023 (MLN): Oil & Gas Development Company Limited (OGDCL) has successfully completed the Khewari (Suleman 1 & 2) Development Project, with potential gas production of 10 million standard cubic feet per day (MMSCFD), the company's filing on PSX showed today.

Currently, 7 MMSCFD of gas is being processed at the Sinjhoro Plant in the Sanghar District, Sindh Province, and will be ramped up to the full potential. The wells are under a choke optimization process for further enhancement in gas supply.

OGDCL adopted a fast-track strategy, accelerating processes for the first gas injection by laying a 6-inch diameter pipeline spanning 14.5 kilometres from the Gathering Facility near Suleman-1 to the Chabaro Tie-in point.

The venture is a collaborative effort in which OGDCL serves as the operator with a 77.50% stake, while Government Holdings Private Limited (GHPL) holds the 22.50% share.